Mariel Project
Boiler – Commissioning:
Chemical cleaning and boiler blowing were completed. Algorithms were tuned and functional groups were tested. Defects and unfinished work are being remedied.
Turbine Hall:
Tests of the feed pump sequence, tests of the lifting oil system, tests of the sealing oil system and tests of the circulation pumps and the seawater system are underway. Tests in the EHV substation, blowing-through of the turbine halls have been completed. The tests progress is limited by damage to the equipment caused by the assembly company.
First synchronization 24.7.2021
Tests of unit performance 20.7.-7.9.2021
72-hour test 7.9.2021
Guarantee measurement 15.9.2021
PAC 22.9.2021