Mariel Project

Boiler – Commissioning:
Chemical cleaning and boiler blowing were completed. Algorithms were tuned and functional groups were tested. Defects and unfinished work are being remedied.

Turbine Hall:
Tests of the feed pump sequence, tests of the lifting oil system, tests of the sealing oil system and tests of the circulation pumps and the seawater system are underway. Tests in the EHV substation, blowing-through of the turbine halls have been completed. The tests progress is limited by damage to the equipment caused by the assembly company.

First synchronization 24.7.2021
Tests of unit performance 20.7.-7.9.2021
72-hour test 7.9.2021
Guarantee measurement  15.9.2021
PAC 22.9.2021
 

Boiler

Boiler

zväčšiť
Burners testing

Burners testing

zväčšiť
Cold tests of turbine after assembly completed

Cold tests of turbine after assembly completed

zväčšiť
Blowing through operation in turbine hall

Blowing through operation in turbine hall

zväčšiť
Completed assembly of  transformers

Completed assembly of transformers

zväčšiť
Completed assembly of generator outlets

Completed assembly of generator outlets

zväčšiť